Construction

IJM FasTrak - the express building process

Construction Sequence

Standard Masonry Construction

Weeks

IJM FasTrack

Foundations

1

Foundations

Foundations

2

Foundations

Bricklayer ground floor

3

Erect timber frame structure, fix & glaze windows

Bricklayer

4

Felt, battens, tile roof

Fix & glaze windows

5

Brickwork & first fix

.

6

.

Roof structure

7

Insulate

Felt, battens, tile roof

8

Dry line

First fix

9

Second fix

Plasterwork

10

Decorate and move in

Plasterwork

11

 

Average building time can be substantially reduced using IJM FasTrak system with significant reductions of on site labour.

.

12

Second fix, plumber, electrician

13

.

14

.

15

.

16

.

17

Second fix, carpenter

18

...

19

Decorate, move in

20

[Login]

[Drawings]

[Why IJM]

[One Stop Shop]

[Why Timberframe]

[ Quote]

[News]

[FAQ's]

[Links]

[Contact us]

[Home]

 

 
Click on the + to expand
   Login
   Drawings & Designs
   Why IJM?
   One Stop Shop
   Why Timberframe?
   Request A Quote
   News
   FAQ's
   Contact Us
   Recruitment
   Home
IJM Timber Frame Construction
Click for larger image