IJM FasTrak - the express building process
Construction Sequence
Standard Masonry Construction |
Weeks |
IJM FasTrack |
Foundations |
1 |
Foundations |
Foundations |
2 |
Foundations |
Bricklayer ground floor |
3 |
Erect timber frame structure, fix & glaze windows |
Bricklayer |
4 |
Felt, battens, tile roof |
Fix & glaze windows |
5 |
Brickwork & first fix |
.
|
6 |
.
|
Roof structure |
7 |
Insulate |
Felt, battens, tile roof |
8 |
Dry line |
First fix |
9 |
Second fix |
Plasterwork |
10 |
Decorate and move in |
Plasterwork |
11 |
Average building time can be substantially reduced using IJM FasTrak system with significant reductions of on site labour. |
.
|
12 |
|
Second fix, plumber, electrician |
13 |
|
.
|
14 |
|
.
|
15 |
|
.
|
16 |
|
.
|
17 |
|
Second fix, carpenter |
18 |
|
... |
19 |
|
Decorate, move in |
20 |